Hi All,
Let's say I run MRP at the beginning of the month with PIR's. 2 weeks later, the PIR's (requirements) change and MRP needs to be run again. Let's say material A had a PIR of 2000 at 1st June. On 15 June, the PIR is revised to 2500. 1000 has already been produced. If I run MRP on the new demand plan, what will happen? How will this be adjusted? Because the system will think that on 15 June, requirement is 2500. How does this scenario work?
Thanks!